- 0:02How's that?
- 0:03Okay, same thing.
- 0:05All right, we are back and third and final of the afternoon planning board. Uh Ron to walk us through what you've proposed and requested for next year. We'll uh ask questions along the way and
- 0:24start our conversation.
- 0:25I based the budget on 14 meetings. 12 regular meetings and two special meetings. It could be more, but often the special meetings are shorter on average than a regular meeting because they're one usually one agenda items. Uh average duration of our meetings uh is estimating two hours. So we'll start with Logan. Um Logan and I have discussed an average number of hours per month of five. uh he arrives based on a 2-hour meeting, but he has an extra hour because he arrives early, sets up the room, uh and so forth. And based on the compensation that I understand, he is uh pre or provided I have a total compensation of $2,400 for the year.
- 1:10Linda averages 12 hours 11 hours a month, excuse me. and based on her compensation, that would be a total of $2,112 per year. Those two together equal the first line, planning board personnel services. The next item is for consultants. Um,
- 1:34Ron, can I just stop you there for a second?
- 1:36The Linda hours that reflect $16 per hour.
- 1:39Yeah.
- 1:40Thank you.
- 1:41And Logan is 40. Uh, Andrew, as I understand it, and Tiffany sent me the contracts this week,
- 1:50and
- 1:52as I understand it, Andrew's compensation is 225 per hour. In 2026, we had budgeted 4 hours per month non-escrow because we were dealing with a complex project, the Bliss Tower replacement. Uh, reduced that to three hours a month in the 2027. I think it's probably a less ambitious agenda as far as we can tell right now. Total compensation for non-escrow related expenses that would be $8,100. Renia estimate uh there was a range there. So I just picked a number of 150 an hour on average.
- 2:30Sorry, who is this?
- 2:31Reneia,
- 2:32the engineering firm.
- 2:33Engineering firm.
- 2:34What's the name of it again?
- 2:36Renia.
- 2:36Reneia. Okay.
- 2:37Renia. um we we rely on them much less per month uh for non-escrow advice. So I budgeted two hours a month there roughly $3,900. So that equals the 12,000 that you see in line two. And in line three that's miscellaneous expenses. It includes the legal postings, general administrative expenses, name pl name plates and that sort of thing. That's actually a little less than was budgeted in 2020, but it's actually the same that was budgeted in 2026. It was amended, so I reduced it back to the original adopted amount.
- 3:18That's my background on the numbers and the process I used to get to.
- 3:22So, in the contract, there's also language that indicates, and I sent a question about this. I'm sorry. the contract. There's also language that it is 1 hour at $225 travel time,
- 3:35okay,
- 3:36to attend the playing board meetings. All right.
- 3:38And I the clarification I asked for whether that was 225 an hour times whatever the actual travel time is or whether it's 225 an hour um for 1 hour. I sent it sent it to you Joe I think for clarification. So I don't know whether I I haven't seen that. So, what's the answer?
- 3:59Uh, for Andrew, it's 225. I believe he charges 1 hour because it's a 2hour round trip,
- 4:04but he he only gets paid for 225 bill when he comes for anything where he uh speaks with the planning board in um executive session or he is discussing litigation or he's working with taxerts and has to go on a bearing court. Those are all at full
- 4:25right. But but tax are not part of
- 4:27I'm saying in general but okay but the contractual bill does not actually have language in it to cover travel.
- 4:35It does.
- 4:36The one for the planning board does.
- 4:39No his contract.
- 4:40I Okay, I'll look at it again cuz I pulled both of them and I didn't see that. Okay. So, but to come back to your thing,
- 4:46you need to budget one hour one for every meeting you need to budget 225 travel cost. So my question back to uh group head is what we try to do is allocate time spread across all of the projects
- 5:02right
- 5:03so uh if we have three projects on the agenda I don't I hadn't had the contract until Friday so I haven't had a chance to really understand I certainly wasn't involved in negotiating it and so this is all sort of knowledge outside of my uh sphere right now but um so so the question would be does Andrew divide his driving time up amongst the projects that are on the agenda or does he charge that to what I would call overhead?
- 5:30To me, that would be overhead.
- 5:31Okay.
- 5:32Um but I'm assuming that the meeting you had this week where the only item on the agenda was uh plus
- 5:38Yeah.
- 5:38that all of the time for that meeting for Andrew will be built to that escort count and that there'll be no charge to planning board. Right.
- 5:45Okay.
- 5:45Is that correct, Margaret?
- 5:48I just don't know. I this has been outside of my my purview so I don't know what the agreement was and u and that's just not a question I've asked our agenda planning meetings are divided amongst the projects that are on the agenda both the engineers and our and the attorney divide that that planning meeting that we have each month before our meeting to the various projects if I'm [clears throat] engaged with Andrew on a more of a a legal question that is higher or not directly related to a particular project that gets build to this threehour overhead but I really don't have an an opinion of the basis for an opinion about how we deal with
- 6:32so in the in the in the past the actual planning board meetings uh the attorney build their time
- 6:40um where if there was a discussion of 15 minutes and they do this for the HBC as well um they allocate their hours based upon the actual uh project that's how they account for their time. So 15 minutes of the time is for a particular project during the planning board meeting that should go to escro. Uh if there's there's an hour going to something else that you go to the escro for that project and that's how it was done in the past. So
- 7:08I think that's how it's done now.
- 7:09Yeah. So to my point the meeting that just occurred for bliss tars 100% of that time should be going to the escrow because nothing else was discussed.
- 7:20That would be my assumption as well. I haven't seen that invoice.
- 7:22When I see the invoice these are the things that I've been trying to verify because in order to approve the invoices I have to see how long was the meeting what was built to escrow. If I know that the meeting was only about one topic, that's the kind of clarification so that we make sure that it's getting appropriately built to the applicant rather than the planning.
- 7:42Understand? And I also ask for clarification on the chair's role in this whole process. Um, and I'm hoping to get some clarity either from you or from the city on what am I authorized to review, approve u because much of the question is dealing with whoever negotiated the contract and I don't know that I'm in a position to interpret that without the benefit of legal counsel or the parties that were involved in the contract. So I'm not I'm not saying I won't do it but I need clarification understand my role
- 8:15to me it's not about I what I cannot do
- 8:18cuz I'm not at the planning board meetings
- 8:21is know that in this 2hour meeting [clears throat] um 30 minutes went to Gristars 30 minutes went to some other building whatever I don't know that the only thing I would ask from you is that [clears throat] you're looking at okay we had a 2-hour meeting 20 minutes of it the general discussion this was very focused blah blah blah so that I can then look at it and tie back to okay this is the correct bill
- 8:47so our process
- 8:48that's all I want
- 8:49our process is that Linda reviews the invoices initially make sure that they are defensible then she and I review it together before we bring it to the board then the board votes on it my understanding that vote was to verify that the consultants performed the task for which they're charging us. That's been my understanding of the process. You're asking me to interpret and analyze things that are outside of my my knowledge. A because I didn't have contracts until Friday. Um and B perhaps outside of my authority. So I just I'm asking for clarity so that I can fully participate in in this part of the analysis. Well, you know, it at the end of the day, the council has to approve paying the bill and uh I want to know if it's two-hour meeting uh how much of it should have been built to escro and and the the basic guideline is very simple.
- 9:46If it's specifically focused on a project, that time to that meeting gets built to escro. And all I'm asking is that a tally be kept so that I know that in a 2-hour meeting 1.5 hours are getting both and.5 [clears throat] that's that is definitely within your purview. I think that's all
- 10:05I think to the extent that you've made other requests. For example, you've asked me to sign approval and I don't know that I have the authority or what that would mean. So that's these are just some of the clarifications I'm trying to to get some guidance.
- 10:18No, that's fine. But I I need um you know if I have escrow bills with the same date as a planning board meeting and the time build to the planning board meeting greatly exceeds the length of the meeting in the first place. That's why I asked the travel question and in addition there's a bill to escrow on the same date. I need to know is that bill to escrow work that occurred and you clarify that that work occurred outside of the planning board meeting or is that half an hour or hour and a half whatever it was part of the planning board meeting. So I want to make sure that
- 10:54we're paying once for the service that's all
- 10:56understand completely. [clears throat]
- 10:57So can I just clarify? So you're getting the invoices you're going through them with Linda. You're signing off on them in terms of the work done but not necessarily approving them. Okay.
- 11:08Correct. I I review it, make sure that it's ready to be presented to the board, then the board votes on it, okay, which I'm a part of, so I do vote on it. I don't have independent authority to either support or not support whatever the board's decision is. I think the larger question I have is what does the board's vote mean?
- 11:27Is it approval to payment or is it just acknowledging that the information is accurate? And I need to inform the board whatever
- 11:35it's the matter.
- 11:36Okay. Um, and then they those go to the clerk's office, right? The clerk's office does the actual processing. So, who signs up? Are you signing off on that as part of the workflow?
- 11:45It has to happen. Yeah.
- 11:46Okay. And then the common council reviews them and votes to pay them.
- 11:51At the end of the day, the common council
- 11:56comes to this is where all of this came up, right? because I was looking at the detail in the invoices and um you know I I happen to have attended one of the meetings which was on one particular topic and the bill was for over 3 hours for that meeting and the meeting was 1 hour and 15 minutes
- 12:14and so that's where I started saying okay we need to actually understand what we're being built for here so the parallel process with HPC is that uh Phil Foreman the the the previous planning board attorney is still the planning board attorney for uh HPC. Uh and she submits the detail. Um he looks at it and says, "Yep, signs off that this is accurate." Uh Lisa Connealy does the same thing for zoning board.
- 12:44She says, "Yep, this is accurate." And then we looked at it and if I had a question, which I did a couple of months ago on HPC, I was looking at some detail on it. Um and I I called Phil. He he was not clear on it. So I I talked to Paul Doro. She answered the question. Problem solved. All very simple. So I'm kind of surprised at how complicated this is because it hasn't been that complicated with the other boards.
- 13:10Well, maybe I'm making things more complicated than I should.
- 13:13I don't I doubt
- 13:14but I also like to know that I'm operating within the rules and the law and that everyone is following the same uh procedures and um I'm kind, you know, and that's sort of my approach to the planning board entirely. I kind of like to run things by the book and if we don't know what the book is then I try to figure it out. So,
- 13:31and to that end I will say that set time up to talk to Andy oneonone to figure out what the lanes need to be and what how we all operate that book together jointly. So, I have guidance.
- 13:44My true objective [clears throat] is to I like scrutinizing books. I think it's important um especially when we're dealing with limited public budgets and we're dealing with other other people's money. So this is not a resistance to to the clarify. I totally understand that. Yeah, I totally understand that.
- 14:02And now that I have a copy of the contract, I'm going to spend a lovely Saturday.
- 14:06It's only it's only a page long [laughter] and and the language relating to the billing is uh two lines.
- 14:14Anything else to add? Uh yes actually I'm going to do the rare instance of saying that I believe you have underbudgeted one of your lines
- 14:21which is the um other line
- 14:24chairman compensation that part [laughter] one
- 14:28um you can see that in 2026 it was 4500 and it's been amended to 5250 that's because there was the 4500 is your uni collapse software
- 14:38ah okay
- 14:40so in last year's budget there was nothing budgeted for these various publications and things. And I'm I'm just looking at what's been charged that against that account because I thought there was software in it. And the software is indeed $4,500 on its own. And then there was 150 bucks to archive past member accounts and set up new email accounts and then there was name plates for 60 bucks and then everything else. Another JB Computers thing for 220. I don't know what that is for, but presumably somebody else does. And then you've got, you know, several publications that like you have my permission to amend that number.
- 15:17What
- 15:17I said you have my permission to amend that number if you can.
- 15:20So I would suggest we amend it back to the 5250.
- 15:23Okay. Mhm.
- 15:24And part of this for me, this is my first time through the process. So I was kind of groping around in the dark on some of these.
- 15:29I think you did a great job for the small amount of time you've been there. So
- 15:34well, as you all are learning probably, my learning curve is time slow. Anything [laughter] else? President Morris. Anything else? Mayor affairs.
- 15:45No.
- 15:45Treasure family.
- 15:47Thank you very much, Chairman Bogle. [clears throat]
- 15:51Thank you. Pleasure. Good luck with your budgeting. You are all set. Thank you, everyone. Thank you. Bye.
Timestamps link to the corresponding moment on YouTube. Auto-transcribed, contains speech-recognition errors. Not an official record.