  1. 0:02Please turn that. Gary, we are ready whenever you are.
  2. 0:10Terrific.
  3. 0:12Thank you for this opportunity. Um, I I just saw this uh the SIB fund spreadsheet here. How would you like to go about this?
  4. 0:22Um, I can't remember what you actually provided. Was it just an emails?
  5. 0:26It was just a uh a a simple uh spreadsheet.
  6. 0:31I think yeah, I think it was in the next set. Okay. Um, basically just talk talk about what your request is and you know, how you intend to use your request.
  7. 0:40Terrific. Great. Okay, so the balance as of um September was uh 383,000. That was left over from the initial loan of 500,000. Our projected income for 2026 is 307,000. Um, what we're last year, we'll go over that briefly. Sidewalk repairs was just over 300,000. Project management management, which is um uh Cropper and Associates was 59,500. Uh miscellaneous, 12,000. That was for the large uh putting together a uh uh reviewing of the of the grant that we did not pursue. And um we did not pay back any of the
  8. 1:30loan as of yet.
  9. 1:31Oh, yes, you have.
  10. 1:32I'm sorry.
  11. 1:33You have.
  12. 1:34We have.
  13. 1:35Yeah, but not much.
  14. 1:36Okay. And that was in what years?
  15. 1:41That was just this first year of this year.
  16. 1:43This year.
  17. 1:43Yeah, the first year we had revenue.
  18. 1:45Right. So, which we had budgeted for 50,000. You went with That's fine. Okay.
  19. 1:49It balanced out the budget.
  20. 1:51Got you. So, what we're looking for this year is and we put out a a bid for this and Excuse me. So, we're projecting um that the repairs that we have that we've went out with it and we've awarded to Vosburg and associates is roughly 273,000. I'm not sure I'm looking at this amended 2026 and I'm not sure where 262 came from. But um I do know that
  21. 2:39So, this is what we received. You generally don't look at like what cash you have remaining generally when you're looking at a budget. It's really more about like having balance. So, you can expecting this amount of revenue, this how you want to spend that amount of revenue.
  22. 2:58Mhm.
  23. 2:59Um So, How much did you say? 383
  24. 3:08Um 383 was the balance in the SID.
  25. 3:13That was what was left over from the initial loan payment. They started out the year
  26. 3:17No, that doesn't
  27. 3:19Because because it's not taking into account other expenditures that have also happened. 383 left of the loan, that means that we would have already paid back 117,000 which is not the case. So, when you say the balance, the balance of which
  28. 3:37We started with 500,000.
  29. 3:40Right.
  30. 3:40And we've calculated all of the expenses since then. That we paid for.
  31. 3:46Okay.
  32. 3:47And that's what we're ending up with.
  33. 3:52So, just the expenses, so not the not the payback of the loan.
  34. 3:56Correct.
  35. 3:57Just literally like the invoices from the construction firms and from the engineering firm.
  36. 4:01That is correct. And any other miscellaneous such as grant writing or publications of uh bids.
  37. 4:09Okay. So then you'd have to take another 57,000 out of that because we took that back to pay to start paying back down the loan.
  38. 4:16Okay.
  39. 4:17Um And you said 57?
  40. 4:24He might have said
  41. 4:25Yeah, he said yeah.
  42. 4:27So straight to the conclusion.
  43. 4:28Yeah.
  44. 4:33Neither of those things.
  45. 4:41Okay. So let's try this from a different direction. So you're starting with the 500k. You're saying that you have 383 left.
  46. 4:59326.
  47. 5:0357.
  48. 5:04Sorry, that 383 was at the beginning of the year left.
  49. 5:09Right. And was there was there was was there not work done in
  50. 5:15Yeah, you had a small amount. Yeah, you only
  51. 5:19work done in the spring.
  52. 5:20The 383 is that what you're starting with?
  53. 5:22No, there was no work done in the spring.
  54. 5:25It it was the 383 your starting point in 2026.
  55. 5:29No. Uh well, I don't know uh to be honest. Um if we did we didn't have any work done, so it would have gone back. I have it as of September.
  56. 5:39Okay. Out of 500k, you're saying 383. 330 of that was in 2025. 3600. So, I'm not sure. Oh, I'm sorry. There's a third Okay. So, let's look at the Yeah. Yes. If you look at the sheet that we have
  57. 6:08Your sheet?
  58. 6:09Yeah.
  59. 6:09Mhm.
  60. 6:10Um so, we start with the 500k, right? And then in 24, we spent 39,738. And then we spent 330 671. So, that's pretty close to and then we're at uh 3619 to date. That leaves you with 125,000. 972 of the original loan. And then You got to take another Let's see if I can get that number. And we got to take that uh 50,000. Okay, that's one alone. So, that leaves you 75,972 remaining of the 500. And then if you add the 307 you do with 382
  61. 7:50172 and then is it 382? Okay.
  62. 8:28Okay. So you're basically wanting to use another almost 118,000 dollars. Of what's in the pool?
  63. 8:46You saying the pool that includes the the assessments? The revenue we're getting.
  64. 8:53No. Um So if you look at the 2027 requested, we're projecting 307,000 dollars basically of income, right?
  65. 9:03Mhm.
  66. 9:03But you're projecting 425,000 dollars worth of expenditures. So you're actually looking to spend more money than we're taking in. Um which I don't think it's the direction we want to go in because especially since we're only paying back 50,000 dollars a year on a half a million dollar loan, that's a decade to pay it off. Which is, you know, not ideal by a long shot and not something OSC will be super happy about. I mean, not people make a bug about it or anything, but it does mean that needs to be recorded differently because it's such a long-term loan.
  67. 9:40Um But how much did you say the contract was that you just let?
  68. 9:47273 or 274.
  69. 9:52And that's the only one for the year, right?
  70. 9:54Yes.
  71. 9:54Okay, so that's going to be over budget by 10 grand. I mean, the general thing when it's a budget for a fund is that the revenues and expenditures match. Um so that's probably how that one and that's how they got to be that 57,000 cuz I just needed something to balance.
  72. 10:12Mhm.
  73. 10:13Okay, balance. But I still only took $50,000 out.
  74. 10:16I got you.
  75. 10:16Against the loan.
  76. 10:28Just a quick question.
  77. 10:29Um if you could just hold off here one second while I'm thinking about this cuz this is this is a whole different weird
  78. 10:35I think. Um Well, so in the effect, even though we brought in the whole 307,000 in 2020, we're only spending through the whole state
  79. 10:51That's all.
  80. 10:54250 Uh $250 for the It's at the year and I can probably have it. Which will only be $1,000.
  81. 11:12I'm just trying to to make sure we're on the right page. So far, there's only been $3,600 year-to-date in expenditures, but
  82. 11:21The actual project management, yes. We did spend that.
  83. 11:25Oh, I believe you spent it. And my husband was almost the exact opposite. He said, "Is that really all you spent?" year-to-date?
  84. 11:30Yeah.
  85. 11:31Cuz they shouldn't be doing that much work.
  86. 11:33Right.
  87. 11:33Okay.
  88. 11:34The big lift was last year when we were looking to populate our spreadsheet with the assessments in it.
  89. 11:41Okay. So, I'm so confused. Uh your spreadsheet says that 2026 year to date is 20,740, but there's only $3,600 recorded in the GL, so are the invoices not getting Really?
  90. 12:02Not that I know. That's best I know. I'd have to look into that deeper.
  91. 12:10See to check that out. $3,906 $3,619. Let me pull it up in case maybe they they billed just that payment and it's not reflected in these numbers.
  92. 12:21No.
  93. 12:21So, don't uh So, sidewalk repairs
  94. 12:25Yeah.
  95. 12:262026 That's
  96. 12:34$3,600
  97. 12:35$3,600 I'm going to make a proposal that I have made in the past.
  98. 12:53Yeah.
  99. 12:58When the sidewalk committee was initially put together, um the DPW commissioner was approved on it, but the DPW supervisor wasn't.
  100. 13:06Mhm.
  101. 13:07The DPW supervisor is the only person who actually has a full-time job that involves taking care of bills and everything like that. I personally think Rob should be part of the sidewalk committee and I don't see any reason why Gary should have to be like unless you love it, unless you want to do it, but I don't feel like it.
  102. 13:26I had a are talking about. During the earlier in the year that you know much of the same reasons but your preference at that time was you know it seemed to me that having Rob on would would make a lot of sense.
  103. 13:42Um only because we were looking at it from the point of view of knowledge or getting things done and that had never been an issue. Budget that's uh you know a new one and uh
  104. 13:52The only thing I mean the fact that we're wondering why there's a $15,000 gap between what we think we've spent to date and what's actually been paid is one of the things that's triggering me.
  105. 14:02Okay.
  106. 14:03Just cuz you know I mean I personally don't think the council people should be involved in that level of minutia like paying bills and things like that not cuz I don't like you guys I just think it's not not your core skill set and you're not you don't get paid to do that and we have staff who does that for a living. And I feel like that's plugged into this somehow better than it has been.
  107. 14:24Okay. I'm fine with that.
  108. 14:27I'll bring that up with Rob.
  109. 14:28Okay.
  110. 14:29Yeah. I I talked to him about it.
  111. 14:30Yeah I have to talk to him about it too and he's perfectly happy to do it. So and when I spoke to you earlier in the year I'd already talked to Rob.
  112. 14:38No. I mean the the the other the other potential option just throwing it out there is that maybe he doesn't have to become part of the board but maybe he could assign his clerk.
  113. 14:49Mhm.
  114. 14:50Yeah. With the responsibility for doing like the bill paying and all of that. For them. That I leave those two concepts with you guys to
  115. 15:02Yeah.
  116. 15:02Can I Can I ask my question?
  117. 15:04Yes.
  118. 15:05So how much revenue have we actual revenue have we brought in from the assessments themselves? Under you know the $100 thing that went out on the tax bills.
  119. 15:16Revenue?
  120. 15:16$307,000.
  121. 15:18That's what I wanted to make sure that is a true number.
  122. 15:20But it's not cash.
  123. 15:22No I know that. yeah. Okay. No, but I just wanted to know that that was in there. Yep, your number. Okay. And I don't know, are you are you guys planning on doing any modifications?
  124. 15:31To that number?
  125. 15:32Yes.
  126. 15:33We're expecting it to go up 10,000 next year. It will continue to go up as more and more properties come online.
  127. 15:45Why are more properties coming online?
  128. 15:47Just with renovations and they'll be taxed to them, assessed.
  129. 15:59I think particularly with any commercial properties like I got with the commercial properties the calculation is based on their assessment as well as other things.
  130. 16:08It's on
  131. 16:09It's on the dimensions if you will. The property line and it's commercial their square footage of the building.
  132. 16:17That's what I thought. So I'm not sure why if if we're not changing the rates, I'm not sure why the revenue would increase. I'm not sure where these new properties that don't exist are being built and are going to now be charged fees for.
  133. 16:30Let me look into it. That's what was presented to us.
  134. 16:38Well, I think for now we just assume it's going to stay flat.
  135. 16:40Yes. Let's assume flat.
  136. 16:42Um Okay. So let's just look at 2026 using roughly your numbers. 20,000 let's assume How much you think you're going to project at the end of the year for the engineering company? Maybe 30? You're at 20. If you say you're at 20 now.
  137. 16:57I'm figuring they'll probably be in another 20 to 30.
  138. 17:02Yeah.
  139. 17:04And I was assuming that we were having a larger number than just 307 available to us.
  140. 17:14Because you were thinking of the balance that was in there. Yeah.
  141. 17:21The number that I came up with for the balance in the loan was 125. Is that what you came up
  142. 17:27No, the balance is 450,000.
  143. 17:31But they've already spent down from the budget.
  144. 17:36What they spend is not related to bonus they owe.
  145. 17:39I'm not talking about what they owe.
  146. 17:41Oh, you asked about the I thought you asked about the balance of the 500,000.
  147. 17:45No, but you're it's the inverse. I'm thinking of what they haven't spent of the balance of 500,000.
  148. 17:52I have 75,000.
  149. 17:53Right, so they made a $50,000
  150. 17:56The 50,000
  151. 17:57this year.
  152. 17:58Yeah, so we're on the same page then.
  153. 18:08So, 275 and you're projecting about 50 for them. Well, that still gets you to like 325. So, your expenditures in 2020 fiscal are going to be about 325 versus income of 319. So, it's pretty close, but overspent by $6,000. So, I mean, even if even if you I would make the argument that more of the loans should get paid back, but let's assume you're not going to do that. That basically means you've got about 76 grand left over from the original 500. Yeah. And then you've got another 307.
  154. 19:15Yeah, that's what I got.
  155. 19:17So that's 383.
  156. 19:19Yeah.
  157. 19:20And then he's got a request of 425.
  158. 19:23So you have to pay 50 out of that 383 towards the loan. So that reduces you to 332.
  159. 19:30I think we should go even higher on the loan repayment. I would say 75.
  160. 19:41Yeah, and if if for some reason the revenues do go up, we can look at that one.
  161. 19:45It's going to be
  162. 19:46So we want to make that 75.
  163. 19:48Yeah, that's what I said. Um So okay, so I just want to make sure this makes sense to you, Gary.
  164. 19:55Yep.
  165. 19:56So we started with the half a million. We spent little under $40,000 in 2024. We spent 330,000 in 2025. We spent 3600 year to date according to these numbers. That leaves us with about 126,000. Um then you have to take out the 50 that we paid back out of the loan for 2026. That leaves you with about $76,000. You add the 307 that's going to be coming in next year on the bill. That gives you a total of 383. I don't know if 383 is probably the best
  166. 20:38way of looking at it, but fine. Um So that would leave you 383 and then if we take 75 out from the loan payment, that would leave you 278.
  167. 20:49I have 307.
  168. 20:52Yeah, I I might be wrong on that one. Let this sink.
  169. 20:57Cuz I took out 50 in the
  170. 20:59this date. That means fine.
  171. 21:02Basically the 75k that that they still have in the pot is going to go towards the loan, and the only revenue, if you will, is going to be the 307. So, they're going to have 307 next year.
  172. 21:16Yeah, no, that makes sense. I'm just wondering why my math is wrong. But, at the end of the day, I'm very tired.
  173. 21:24It's okay.
  174. 21:29And it's unclear this year the total sidewalk repair is going to be 274.
  175. 21:33I find it hard to believe.
  176. 21:35Yeah, the 25k currently is going to go towards the loan, so the only revenue really is the 307.
  177. 21:40So, the 325 that you're projecting for repairs, um but that's probably going to have to be looked at cuz that also has to have in there not just the repairs, but the engineering and everything else.
  178. 21:54Exactly.
  179. 21:55Right. So, that's going to have to be looked at again.
  180. 21:58And you think it's To your point, it seems like there was a a huge amount of work in 2026 for the engineer. Um in 25.
  181. 22:07In 25? I don't believe 3619 number.
  182. 22:12No, cuz the shared total is going to be 274, right?
  183. 22:16No, but
  184. 22:16That's the That's the actual repair work.
  185. 22:19Yes.
  186. 22:19Yeah.
  187. 22:21I I think that 3619 number has something wrong with it.
  188. 22:25Oh, I think there's something wrong with that, too. Yeah, so I mean, basically, if you take the All right, so if you want to go that much further, you take your 76 that's left over,
  189. 22:42Mhm.
  190. 22:43and take another 30 out of it, if that's what you're projecting.
  191. 22:47Mhm.
  192. 22:48Are you You're really spending 50 grand a year with the engineers?
  193. 22:52Um I have I don't have any I I do have it here. Um I can tell you exactly what we've been paying. And no, it hasn't. It hasn't been, but I'm building in a little fluff just so that we cover everything.
  194. 23:09Well, I think I think it's also going to be things where maybe we don't really have to know now, but the reality is you've basically got $307,000 that you can allocate among actual repairs, the engineer, and any other costs that that we might incur. I think that's probably the easier way to look at it. But yeah, even that 307 number might be a little high cuz if there's another 20 to $30,000 outstanding for the engineer in this year, it's going to knock that down, too.
  195. 23:48So, we have a resolution from SID that we will be looking at on Monday um for continuing their the contract with um Crawford with Crawford has um expired. Um so, this was to renew their contract um not to exceed 20,000 without prior authorization of the council.
  196. 24:12Yeah, but for what period of time?
  197. 24:14It's It is for It's starting now because they have they have expired.
  198. 24:19Yeah.
  199. 24:19So, it it expired at the end of August.
  200. 24:22But when is the new agreement intended to expire? December or sometime next year?
  201. 24:28It doesn't have a date attached. I don't think we have a date attached to it.
  202. 24:32There is no date on the on this resolution. No, there. So, we We didn't have a date on that. Um but we We need to go back and look at Crawford invoices because I am quite sure we have paid invoices to Crawford.
  203. 24:51We have what?
  204. 24:52I'm sure we have paid invoices to Crawford.
  205. 24:54What should we have?
  206. 24:55So, that's that's the problem with the 3619.
  207. 24:59Where
  208. 24:59And that's how Where is the So, there's like We've got You've got a year-to-date. I don't know how the number What's the 36 and
  209. 25:06And so, this conversation is clarity.
  210. 25:09Right.
  211. 25:10Yeah. So, then that's 3619.
  212. 25:12That's it.
  213. 25:13Yeah.
  214. 25:13Okay. So, that it's all back-loaded in the in four in Q4 for this year? Is that what you're anticipating that all their billings will come in?
  215. 25:20Well, that's
  216. 25:21I don't know. There's
  217. 25:23So, I mean, it's a high number.
  218. 25:25And I was just looking to
  219. 25:26We don't know. And that we can count.
  220. 25:32So, what you're saying is that the expenditures likely for this year are not going to be as high as we had anticipated because that big gap in um He's saying that 3619 is current. What's the current number?
  221. 25:48Let's Let's put it Like I We don't have all of our documents in front of us. Let's Let's take a look and see what the invoices are for Vosburg, for Crawford and Sons, for all of this, and then we can have a better sense of what the numbers actually are for this year, and we'll know what they are for next year based on what we have at the end of this year. This is Yeah.
  222. 26:10You're on the board, right?
  223. 26:12Mhm. Who brought all the money?
  224. 26:33The number that I He Yeah.
  225. 26:35No, no, no, but I don't see
  226. 26:37I want to get to All right. To be continued.
  227. 26:42Yeah.
  228. 26:43All right. Thanks, Gary.
  229. 26:44Thank you.
  230. 26:45Have a great weekend.
  231. 26:46You, too. Are you leaving me?
  232. 26:56We have to end the meeting. Yes. Thank you everybody.