At a glance
The Hudson Housing Authority board extended its 2023 agreement with Mountco, the Bliss Towers developer, for one year to October 21, 2027, adopted its 2026-2027 operating budget and ratified a new Teamsters Local 294 contract running to June 30, 2028. The executive director and Mountco celebrated the Planning Board's approval of the Bliss Towers site plan and said the next steps are a state sign-off on the environmental cleanup plan, a building permit review by an outside consultant the project will pay for, and a closing that could come within about five months. The board voted down a $51,500 purchase of a used 2023 pickup, 5 to 0, then authorized the executive director to spend up to $50,000 on a truck with a plow and salter, ideally with a warranty. During public comment, residents described a neighbor they said harasses and threatens them, and a resident who moved out of a damaged apartment eight months ago asked when it would be ready. Officers were also elected. The video was posted October 22, the day after the meeting.
Roll call, September minutes and bills
The meeting opened at 6:03 p.m. The board approved the September 2026 minutes and, after questions about specific payments, the September accounts payable.
Key points
- A commissioner asked what several payees on the bill list were for before voting. The executive director explained a mileage reimbursement for a maintenance worker who has been using his own car to pick up supplies because the authority has no vehicle.
- Another payment was to an outside Section 8 inspector. Staff said inspections used to be done in house but are contracted out now because the authority is short-staffed, and some landlords failed and needed re-inspection.
- Board members disagreed about whether line-by-line questions belong in the meeting or in emails to the executive director after the package is sent.
- The accounts payable for September 2026 were approved.
Bliss Towers: site plan approved, state steps next
The executive director marked the Planning Board's approval of the redevelopment's site plan. John from Mountco, the developer, laid out what remains before the project can close on its financing.
Key points
- Mountco praised the Planning Board's review, saying it kept the public hearing open for several months and visited the site.
- The project is in the state Department of Environmental Conservation's Brownfield program. The state is reviewing the plan to clean up contamination on site B.
- The main funding is tax-exempt bonds and tax credits from New York State Homes and Community Renewal, which will not close until DEC signs off on the cleanup plan.
- The city agreed to let the Housing Authority hire an independent consultant to review the building permit application for the city, because of the project's scale. Mountco said the cost is a project cost paid from development funds, and that the review should take about two months.
- Asked about timing, Mountco said a closing could come within about five months, depending on the state, and that construction starts after closing.
- Mountco said it has done about 30 similar projects and has never gotten this far without closing.
- Speakers stressed the outside reviewer is not a criticism of Hudson's code enforcement officer.
- Planning Board review of the HHA / Mountco Bliss Towers Redevelopment site plan
- Hudson Housing Authority meeting, September 16, 2026
Residents describe harassment by a neighbor
Residents told the board a neighbor on their floor curses at and threatens them, including with a taser, and asked that she be moved to another floor.
Key points
- A resident said he has filed many complaint forms and that police have not resolved it, and that he should not have to move.
- A family member said her children are afraid to go out and asked the board to move the neighbor rather than her family.
- The executive director said the authority is pursuing legal processes, which take time, and cannot evict or move someone on its own without a court-ordered procedure. He said apartments that could be used for moves are offline.
- A commissioner said residents will get first choice of floors and neighbors in the new buildings.
- A resident said a taser counts as a weapon; later in the meeting another speaker argued it becomes illegal only when used to threaten someone.
Residents who spoke are not named on this page.
Eight months waiting for a repaired apartment
A resident moved out of a low-rise apartment in an emergency eight months ago asked when the repairs will be done.
Key points
- She said she has been told repeatedly that the unit is almost done, and asked not to have to move in the middle of winter. She has an adult son who needs a quiet place.
- The executive director said the authority has one maintenance worker and one temporary worker, and that emergencies have taken priority.
- He said hiring is limited by a lack of qualified applicants, not the budget; the job is posted on the authority's website and the New York State Public Housing Authority Directors Association site.
- Commissioners suggested bringing in an outside contractor. The executive director said work would have to be bid and the maintenance union contract limits what can be contracted out, and that the idea was recently discussed.
- Board members said the authority would try to get the resident a firm date.
Board officers elected
The board held its annual officer elections, which it missed in September.
Key points
- A chair was elected without opposition.
- Mary Decker was re-elected vice chair.
- A treasurer was elected.
- The executive director said a resident commissioner election is coming. The current resident commissioner's term runs to December 31.
The captions do not give the full names of the chair and treasurer clearly, so they are not named here.
Mountco agreement extended one year
Resolution 562 extends the September 18, 2023 memorandum of understanding with Mountco for the redevelopment. It passed on a roll call vote.
Key points
- The resolution says the agreement's deadlines for finalizing plans and financing have passed but significant progress has been made.
- It authorizes the executive director to negotiate and sign an extension through October 21, 2027, or another date needed and approved by legal counsel.
- The item came back after commissioners asked last month to see the agreement and consult counsel on how long an extension should run.
- A commissioner pointed out the developer's name is spelled two ways in the resolution; the executive director said he would correct it.
2026-2027 operating budget adopted
Resolution 563 adopts the budget for the year July 1, 2026 to June 30, 2027. It passed on a roll call vote.
Key points
- The executive director said the budget is usually adopted before June but was delayed by accountants who left mid-work and by two missed meetings in April and May. A new firm is now in place.
- Asked about legal costs, he said legal fees for the redevelopment are kept separate and will be paid from the development budget at closing, not from operations.
- Last year's insurance settlement of $23,000 for the maintenance truck that caught fire was raised in connection with the vehicle purchase.
- A commissioner noted raises for employees, which the executive director said were part of the union negotiation.
New Teamsters contract ratified
Resolution 564 ratifies a memorandum of agreement with International Brotherhood of Teamsters Local 294 for a successor contract from July 1, 2026 to June 30, 2028.
Key points
- The previous contract ran from October 1, 2024 to June 30, 2026.
- The union ratified the agreement on September 30, 2026.
- The board ratified it on a roll call vote with no questions.
Truck purchase voted down, then a $50,000 cap
The board rejected Resolution 565, the purchase of a 2023 Chevrolet Silverado 2500 for $51,500, and instead authorized the executive director to buy a truck for up to $50,000.
Key points
- The authority has had no maintenance truck since one caught fire, along with its plow and salter.
- Commissioners questioned the price of a used 2023 truck with about 65,000 miles and no warranty, and asked whether a regular cab would do.
- The executive director said he wants a truck before snow season, to avoid liability.
- The resolution failed on a roll call vote, with every commissioner voting no.
- The board then voted to authorize the executive director to spend up to $50,000 on a new or gently used four-wheel-drive truck, ideally a regular cab with a snow plow and salter and a warranty.
- A resident asked for a temporary dumpster for bulky trash until a truck arrives, since the trailer used for monthly cleanouts needs a truck to move it.
The dealer's name is rendered several ways in the captions.
Closing public comment
A speaker suggested mental health support in the harassment case and offered to help find job applicants.
Key points
- The speaker said moving the neighbor around would not fix the problem and suggested getting her help.
- The speaker asked about certification requirements for maintenance jobs; the board pointed to the job descriptions on the website.
- The meeting adjourned.
About this page
FUTURE HUDSON is an experiment in civic engagement: every public meeting of the City of Hudson since January 2026, transcribed and made readable, so any resident can follow what the city is deciding without attending every meeting. This page covers one meeting; see the full archive.
How it was made
The meeting video was transcribed automatically; the transcript was then organized into sections and summarized. The raw transcript is above, every claim can be checked against it.
What to be skeptical of
The transcript is automated and contains speech-recognition errors; names and numbers may be wrong. This page has not been reviewed by a human. Nothing here is an official record, the city's official minutes are authoritative.
About coverage of this body
Meetings of the Housing Authority are uploaded to the city YouTube channel by members on a best-effort basis (not by the city audiovisual coordinator, who posts only the Common Council family, Planning Board, and HCDPA). If a meeting of this body is missing from the archive, it usually means the recording was not uploaded. See the archive index for the full coverage note.