  3. 0:12First order of business under general business is approval, approval, and payment of bills. Um, just so you understand the process that Linda and I have put in place, we, we review the invoices before we bring them to the board, make sure that the invoices are lined up with what we understand the work that has been accomplished. So, we wouldn't bring it to the board if we didn't think that the invoices are in order. However, if you ever wanted to see an invoice or have more information, um, just let us know. Uh, if, if you feel like you're not getting enough information today to make it an informed and responsible decision. So with that in mind, uh, a motion to approve, uh, payments as listed in the agenda is in order.
  4. 1:01Second.
  5. 1:01Um, please. Chairman Bogle?
  6. 1:01Yes.
  7. 1:06Missra, yes.
  8. 1:07Miss Black, yes.
  9. 1:08Mr. Schvy, yes.
  10. 1:10Mr. Spear, yes.
  11. 1:12Mr. Wood, yes.
  12. 1:12Motion pass is approval of minutes as distributed first. Are there any edits or corrections to the minutes as distributed, a October 13th and October 19th minutes? Any edits or corrections? Hearing a motion to approve is order. So we do have a motion to approve.
  13. 1:33Second. I second.
  14. 1:33Was that Sarah? Okay. Um, item three on the general business lays on reports. These details, would you call the role, please?
  15. 1:52Chairman Bogle, yes.
  16. 1:53Mr. Schesky, yes.
  17. 1:54Mr. Spear, yes.
  18. 1:55Mr. Woodall, yes.
  19. 1:57Miss Cora, yes.
  20. 1:59And yes.
  21. 2:00Okay. Now, lon reports. Any, anything to report from our leazison on relationships?
  22. 2:05I did not make it to the meeting. Don't ask me.
  23. 2:05Um, then, uh, finally, uh, on the financials, u approval to release the escrow for EPF Hudson parking lot. Is there any background on that, Linda, that we need to know?
  24. 2:21Well, there may be one more outstanding invoice from the engineer. We're just waiting, but we would like to get it.
  25. 2:33Not if this bill was outstanding, we shouldn't be approving it. That's my opinion.
  26. 2:38Yeah, you know, well, we just approved payment of tonight.
  27. 2:45There might be. He's checking. There was a question of whether there was a outstanding review. Yeah. And we think that they've done it maybe three months ago. Right. Yeah. But sometimes it takes that long.
  28. 3:02Let me ask, our engineer is on. I believe our engineer is on now.
  29. 3:02You just have your lawyer on.
  30. 3:08Okay. I assume, Andrew, you have no point of view on that.
  31. 3:14No. Hi, everyone. Uh, not really. I'll let the engineer speak for themselves on this. I understand they were just looking at the applicant's compliance with conditions of approval from this board. So, that's what might generate the, uh, extra charge to be paid.
  32. 3:32Any other objections on, on approving this or anything?
  33. 3:43I'm sort of with Eugene. If there's a possibility we may still owe money, like, and it may not be a small amount either. It could be a larger amount if you give the money back and we, years past, run into a problem.
  34. 3:50Yeah. Same thing, and two years later it was still kind of
  35. 3:58Is it possible to make it conditional, like, upon receipt, if, you know,
  36. 4:05Because I can easily hold it, but I just won't submit it.
  37. 4:05And I think there's, like, also, it's pocketbook factory. Yeah, it's like the scale, like, they're in a scale that this can't be, it seems very unlikely this be financial hardship, I guess, to them.
  38. 4:20But let me ask, let me follow up on suggestion that we pass it as a contingent so that we don't have to wait a full months.
  39. 4:27Yeah.
  40. 4:31If they take care of their business in the, in the coming weeks.
  41. 4:31Okay.
  42. 4:34Okay. So, motion to approve contingent on the finalist. A motion order.
  43. 4:41I make the motion.
  44. 4:41Okay.
  45. 4:41Second.
  46. 4:50We have an section, please. Um, so we're going to vote on, we're going to vote on, oh, yes. Okay.
  47. 5:01Yes. Mr. Con? Yes. Mr. Woodall? Yes. Mr. Spear? Mr. Shadesby.
  48. 5:06Yes.
  49. 5:06Uh, final item on regular business is training requirements. As we all know, we're required to four hours of training in each year, calendar year. Uh, at this point, Jean has 3.5. Nathan has three. You're done.
  50. 5:24I think there is three. I have three.
  51. 5:24The rest of you have zero. Um, in our monthly agenda meeting, which I'll tell you about in a minute, Andrew offered a, a proono service to the board. Andrew, would you speak to us about what you're proposing?
  52. 5:43Sure. Just to give the board some of its training requirements, go over whatever topics you guys would want to hear about, because we do conduct a lot of training for other municipalities. So, just wanted to make the offer there, because I know some of us were, uh, not dragging, but just not, not quite over the threshold yet.
  53. 6:01Strange language.
  54. 6:14So Andrew has offered two hours before the end of the year, which is great. Proono, I want to underscore that this would be as a service to, uh, the Hudson Planning Board.
  55. 6:23I, I will need a specific topic, because it has to be in the form of a resolution to the council, right? Because the council does have to approve your training, otherwise it wouldn't count.
  56. 6:37Oh, I know. That's great.
  57. 6:43So we'll get more information to you on this as details are resolved, and if you need it,
  58. 6:43I need it by the end of the week, because I have to submit it for the informal meeting.
  59. 6:51Andrew, what topics might you suggest?
  60. 6:57Well, we do case law updates a lot. Those are interesting. Maybe a seeker overview might be beneficial for the board, but I'm all ears if there's anything anyone else wants.
  61. 7:15Uh, there seems to be a lot of, I mean, I feel like in our last big consequential decision there was a lot of debate about, or a lot of discussion about the role of the board, the public process, shaping development, you know, plans for the city. I don't know if there's, like, a general topic of the Planning Board's purview, or, or I don't know.
  62. 7:43Yeah, even in the, or, I know there in the context of charter reform. I don't know, something like, is, does the Planning Board's role need to be adjusted in the context of charter reform?
  63. 7:55Maybe something around jurisdiction and authority, something like that, if you'd all be interested in.
  64. 8:01Yeah. Yeah. But, and I can keep it, keep it broad. Maybe, uh, general Planning Board requirements, things like that.
  65. 8:10Compliance with city law, code compliance, right?
  66. 8:17I did want to raise, um, we have email about this. Um, but we, the city is not currently a member of the New York Planning Federation, which does have a whole giant library of training materials. Um, I think it would cost the city $320 odd dollars a year to be a member, uh, and get access to that. Um, I don't know if that's a thing that we as a board would like to advocate the city do in the future, but, like, I personally think it would be good, a good idea. They have a really sort of large catalog of trainings on there, and an annual conference, if that's something you wanted to spend a Monday sometime in April on.
  67. 8:56Actually, their resources are applicable to more than just planning and zoning points.
  68. 8:56That's a city one.
  69. 9:05Yeah. Yeah.
  70. 9:06I would say that the category on the agenda, that's an appropriate issue to raise. I think the question would be, how does the Planning Board make that request to the city, especially during budget time?
  71. 9:14Wait till after.
  72. 9:22Wait until after the vote.
  73. 9:25Till after the vote. Okay. That's why the budget, um, is the key.
  74. 9:30So before we move into new business, I, I wanted to talk about one of the procedures that the Planning Board does in preparation for meetings that, that, uh, might be helpful for you. Uh, the deadline for any applicant to submit materials, it's almost two weeks before our monthly meeting. Um, then usually 10 or 12 days before the meeting I convene a meeting with Linda, Andrew and the engineers. We review the application materials that are in front of us. We discuss, uh, the agenda, finalize the agenda.
  75. 10:01Uh, sometimes the strategy discussions about how come will be presented. So, if, if you have questions about the agenda, that the opportune time to address those to either Linda or me would be just in a few days past the monthly deadline. Um, if you have questions about a topics that might be on the, or something you might like to have on the agenda, for example, Nathan, a request might be, I'd like to put some information on something on the agenda at training requirements. Um, and so, but, uh, I'm not sure that we ever shared that schedule with the board before. And then usually a day or two after we finalize the agenda, then Linda forwards that on to, onto the board. Okay.
  76. 10:43Yeah.
  77. 10:51The portal under the meetings tab posts the deadline for submissions as well.
  78. 10:51All right. Uh, moving on into business, we've been asked by the city, uh, to offer our opinion on a proposal of the law change. Uh, it's regarding a one-year moratorum on the approval of battery storage facilities. Um, the city's not certain that our opinion is required, but they're asking for it just to be extra, extra cautious. And I think that the, what they're asking is a one-year moratorum in order to be able to evaluate the impact of lithium battery facilities within our community, safety aspects, as access for fire and safety and other kinds of considerations. And I don't see any obvious reason why we wouldn't support that. But before we open it up for discussion, Andrew, do you have any insight on for the board?
  79. 11:52No, that's generally it. I, I reviewed the proposed law. It's just the city enacting a moratorum, essentially saying stop. You can't build these for a period of time while the city updates its code requirements. We see this frequently whenever there's new sorts of development. It's just a, a land use tool to protect the city, so you can get out ahead of things.
  80. 12:16And, uh, yeah, in the referral email it wasn't clear that the recommendation was required, since it's not really amending the code, rather just putting the mortorium in place, but, you know, out of an abundance of caution, here we are. So I think that the council's just looking for a general favorable, disfavorable position on it, recommendation.
  81. 12:41Thank you. We know the city will be undertaking code, re, zoning reform over the next 12 or 15 months. So apparently this is the, the request is based on the ability to incorporate that into future zoning. Any discussions from the board on this?
  82. 13:00What, do you know what precipitated this? Is there, is there a project coming down, like, is there something going on that we don't know about?
  83. 13:03They've had two or three inquiries from these companies and, uh, specific sites that would place, uh, these facilities adjacent to residential neighborhoods or other kinds of commercial or public access space. And so, um, that, to my knowledge, that's what, what raised this. I also know that just reading your paper that other communities have been dealing with some of the same issues.
  84. 13:28There's something at Athens. Did they do a moratorum?
  85. 13:38Yeah. Yes. Did they pass moratorium?
  86. 13:41I don't know that they passed. I know that they were in the process of doing it.
  87. 13:45Okay. And I kind of think that it's almost like putting the cart before the voice. Um, I've got big scenes on it. Um, do we really need it? I mean, anytime a project comes through, it comes through the Planning Board. We do debates, deliberations, public hearings, and if something like this were to come through, then they would have to go through the same process, and we as the Planning Board can deny the application based upon facts that we discovered during the process.
  88. 14:18Um, unless zoning doesn't jump to a facility of that nature. If, as we learned in our other decisions, we have to follow what, what zoning laws are in place.
  89. 14:25Yeah.
  90. 14:25And if they don't restrict that kind of facility, then we wouldn't have the authority to be able to deny it on the basis of that.
  91. 14:32Great job. There's no restrictions on a trade like that.
  92. 14:43Correct.
  93. 14:44No restrictions. So again, if they were wanted, they would have to come to the Planning Board anyway, and we would take it from there. If necessary, then it would go through the sewing board if changes are needed. Isn't that usually the case?
  94. 15:00Or wouldn't they be, they would be unregulated? So they'd be able to do whatever they want in the proper zone.
  95. 15:00Yeah, I think probably from where we sit, we're not able to see the full dimension of the question that the Common Council can see, right? And, and so I think just offering our support for a one-year moratorum seems to be a, a reasonable request, but other discussion.
  96. 15:26Yeah, I had, um, I think the mortorium makes a lot of sense. Um, I had some conversations with people about the technology and the, and the, the risks and the benefits, and, um, yeah, so I was, um, I guess reassured that the moratorium makes a lot of sense and seems reasonable. It also occurred to me that maybe I'm, you know, I mean, I'm just always looking for an opportunity to convene, you know what I mean? And to sort of, you know, because I think this, a battery storage center is sort of data center adjacent in a way. There's sort of a fear kind of thing about it.
  97. 15:59Um, that maybe there's a possibility for just having some sort of community conversation about the grid, and what, what is bad, what, what are the benefits that battery storage actually brings to a community, because I think it does, there are benefits and there are risks, and we should, whatever process the city engages, we could be supportive of how the, how we all sort of educate ourselves about the best sighting.
  98. 16:23Um, yeah. I know, um, I'm freent frustrated by the way that removables often get, like, stuck with, like, ownorous restrictions, and then we breathe the air from the Athens generating plant, um, as the consequence. That's the other side effect. Um, but I think in this case, it's like a year-long moratorium to get the zoning in order feels like fine, and like a good plan for a new technology. The city zoning didn't conceive of battery storage, and I have no idea where are, what the fire department thinks about any of these things, and so seems like a, a year is not very long in the grand scheme of things.
  99. 17:06Any thoughts from that? Um,
  100. 17:12Yeah, I mean, kind of taking everyone's, uh, thoughts into consideration, I think everyone makes good points. Um, I also think it's one of those things that we all use, you know, so to kind of, if everybody's denying it, that, you know, what is that consequence? So, I think it's kind of something that, um, you know, just needs to be managed properly, right? Um, and I suppose if we need a year to figure that out, um, you know, so that these facilities are done safely, and, you know, in a, in a proper way, um, then, you know, I, seems like the right thing to do.
  101. 17:58Um, well, I'm not sure, like, what the use case is where a facility, I guess I need to think about the industrial boundaries of Hudson 2. This would be like a sort of perimeter industrial facility, maybe attendant to increased power, electric infrastructure, but I don't, I don't, I don't know enough about facilities, but it does sound like the runaway, like, meltdown risk can produce, like, noxious chemicals, and, yeah, so.
  102. 18:29I'm not hurting over a year of lost.
  103. 18:29This may not be relevant, but we have a limited amount of, of land in Hudson.
  104. 18:38Yeah.
  105. 18:38And, and we ought to be strategic about how that land gets occupied. I, that was my first thought when I saw this on the, you know, that I, I was surprised that there was even a space in Hudson, because usually they're rather large facilities, right?
  106. 18:53My, what I feel like, what I was told is that the risk is fire, and it's a real risk, and the, the treatment is to let it burn. There's not, you can't really.
  107. 19:00Yeah.
  108. 19:08Yeah. You can't thermo.
  109. 19:10Yeah. Yeah. And so it's almost like a tiger fight.
  110. 19:14They might go and get a motion to the floor to support the, the request from the city council or the county council that the Planning Boards one year.
  111. 19:22One more thing.
  112. 19:22Yes, sir.
  113. 19:22Does, does it look like, sound like that we're going to be picking and choosing applicants in the future, or
  114. 19:30I think that's the, I think what this, what this does is a lot is create a policy that makes that decision for us, as opposed to us doing it one on a oneoff, right, saying, oh, we don't want it there, you know. Is that your question?
  115. 19:47Well, if a company wants to come in and, right now we're saying no with a moratorium. Are we going to do that next month with another company, and then next year with another company? Are we setting a resident, you know, of stopping projects where we're trying to freeze projects for the city, for the ware of the city? You know, that's the flip side of it. You know, the angels on the side, on the side.
  116. 20:17So another way of looking at a moratorum is it treats every potential applicant exactly the same.
  117. 20:26Yeah. And I think what Jean was saying was not necessarily an applicant for the same thing, but an applicant.
  118. 20:26Yeah. And that's generally any sort of project that we may feel unsure about, and then we create a moratorum, and the Common Council is asking for our opinion because they might not themselves. So they want, they want other people to come in, jump on board. So when the crap hits the ban, we're all going to get it. Then us and whoever else are requesting support from, and that's what I'm trying to avoid.
  119. 21:00So what triggers a Common Council request? Do you mind speaking to that, Linda? How does that process work?
  120. 21:14Whenever there's an amendment to code and it involves land use specifically, it requires county planning board review, which also requires city planning board review.
  121. 21:30So this is a part of the secret process.
  122. 21:33So this is not a unique process. This is the standard process. Okay.
  123. 21:37Yeah. Your, your code requires the referral.
  124. 21:44And whereas our vote is a, um, symbolic vote, the city, the county, excuse me, the Common Council vote is the real vote.
  125. 21:44Yeah.
  126. 21:53Isn't even a vote?
  127. 21:53Well, they would pass them. They are voting on this.
  128. 22:01It would be a vote from us in support of,
  129. 22:01So then, yes, it is a vote for them.
  130. 22:08Yeah. You're, you're doing an, a favorable recommendation or not favorable, essentially an up or down.
  131. 22:18We considered this for the Colorado, like, permit, use permit interpretation.
  132. 22:18Yeah.
  133. 22:25Which just evaporated, right?
  134. 22:29Oh, yeah. We never really had to be questions.
  135. 22:31Andrew, would you give us the proper language for this motion?
  136. 22:37Sure. One second. I'm going to read from your code section. So, I mean, just going off what I'm hearing, I think it would be a motion that the Planning Board issue a favorable report on the proposed amendment from the Common Council and find that it's consistent with fulfilling the purposes of the comprehensive plan.
  137. 23:06Yeah, I will, Andrew.
  138. 23:06The motion has been made by Sarah. No, I can discuss. And Nathaniel, are you second?
  139. 23:13Sure.
  140. 23:13Okay. Any further discussion? Further discussion? Would you call the role, please?
  141. 23:18Chairman Fogle? Yes. Miss Black? Yes. Miss Cocker? Yes. Mr. Hortall? Yes. Mr. Spear? Yes. Mr. Schedy? No.
  142. 23:29Being that the, there is nothing else on the agenda, than a motion to adjourn to be in order.
  143. 23:29No. What?
  144. 23:36I thought about doing motion.
  145. 23:41I make a motion to rejoice.
  146. 23:41Second.
  147. 23:41With that, wishing everybody happy Thanksgiving.
  148. 23:41Happy Thanksgiving, everybody. See you.